Melrose Council Search

Appropriations & Oversight Committee — 2026-10-19

Appropriations & Oversight Committee 10/19/26

This meeting starts at 0:00 in a recording that covers several meetings.

Attendance

Jason Chen present · At-Large; Cal Finocchiaro absent · Ward 6; Bradley Freeman present · President, Ex Officio; Maya Jamaleddine present · At-Large; Manjula Karamcheti absent · Ward 1; Elizabeth Kowal present · At-Large; John Obremski present · Ward 2; Christopher Park present · Ward 3; Kimberly Vandiver present · Vice Chair; Ryan Williams present · At-Large

Agenda

  1. CALL TO ORDER (0:00)
  2. Attendees (0:14)
  3. MINUTES APPROVAL (0:24)
  4. Appropriations & Oversight Committee Meeting September 28, 2026 7:20 PM (0:33)
  5. PUBLIC COMMENT (0:38)
  6. GRANTS (1:17)
  7. Acceptance of a grant in the amount of $2,385.92 for staff time spent assisting with or promoting SNAP applications. (1:24)
  8. APPROPRIATIONS (8:57)
  9. Requesting the Appropriation of $2,976,462 which includes $115,000 previously appropriated for the Feasibility and Schematic Design Cost on December 1, 2025 for the purpose of paying costs of installing a new roofing system for the Learning Commons at Melrose High School. (9:05)
  10. ORDERS (20:08)
  11. Authorization to Execute Lease Agreement: five-year lease agreement with All American Investment Group, LLC for the purchase of a new 2026 Vactor Sewer Truck (20:15)
  12. Authorization to Acquire two Parcels of land- G7 0 111 and G7 0 112- located in the City of Melrose, at their assessed value, to be used for stormwater management, using funds made available through the City’s FEMA Building Resilient Infrastructure and Communities (BRIC) grant. (24:08)
  13. ADJOURNMENT (34:46)

Minutes

Appropriations & Oversight Committee Monday, October 19, 2026, 7:00 PM City Council Chamber, 1st Floor 562 Main Street, Melrose, MA 02176 MINUTES I. CALL TO ORDER Kimberly Vandiver Vice Chair Jason Chen Cal Finocchiaro Maya Jamaleddine Manjula Karamcheti Elizabeth Kowal John Obremski Christopher Park Ryan Williams William Bradley Freeman President, Ex Officio Devin Romanul Chair Meeting was called to order by Chair Romanul at 7:00 PM Attendee Name Title Status Arrived Kim Vandiver Vice Chair Present Jason Chen At-Large Present Cal Finocchiaro Ward 6 Absent Maya Jamaleddine At-Large Present Manjula Karamcheti Ward 1 Absent Elizabeth Kowal At-Large Present John Obremski Ward 2 Present Christopher Park Ward 3 Present Ryan Williams At-Large Present William Bradley Freeman President, Ex Officio Present Member Devin Romanul Chair Present II. MINUTES APPROVAL 1 A. Appropriations & Oversight Committee Meeting September 28, 2026 7:20 PM Motion to Approve the minutes by unanimous consent without reading made by Chair Romanul All were in favor and motion passed RESULT: ACCEPTED [UNANIMOUS] AYES: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams NAYS: None ABSENT: Cal Finocchiaro, Manjula Karamcheti III. PUBLIC COMMENT When: Oct 19, 2026 07:00 PM Eastern Time (US and Canada) Topic: Appropriations & Oversight Committee Meeting Join from PC, Mac, iPad, or Android: https://cityofmelrose-org.zoom.us/j/91566868819?pwd=hnIaMj5VCJu2uv0iECFvfDzkohaEir.1 Passcode:437499 Webinar ID: 915 6686 8819 Motion to Open public comment made by Chair Romanul at 7:01 PM There were no comments on the floor or via Zoom Motion to Close public comment made by Chair Romanul at 7:01 PM IV. GRANTS

A. (ID # 2026-1860): Acceptance of a grant in the amount of $2,385.92 for staff time spent assisting with or promoting SNAP applications. Erica Drummond, Director Council on Aging, explained that this is a partnership between the Department of Transitional Assistance and UMass Chan Medical School, and they develop community partners in residential communities who can assist with applying, recertifying, and checking on the status of SNAP and DTA accounts. Her office assists Melrose residents with these services and the grant will help to reimburse them for some of their work. Council asked if she saw an increase in SNAP benefits the past couple of years, and she has for this and other emergency needs as the cost of things continues to rise. Council on Aging has a Social Services Team consisting of Erica, Rachel Cordella (social services coordinator, and an intern, and they help people of all ages with SNAP benefits and Melrose Emergency Fund requests. Motion to Recommend made by Councilor Vandiver Seconded by Councilor Williams All were in favor and motion passed RESULTS: ACCEPTED [UNANIMOUS] TO: City Council AYES: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams 2 NAYS: None ABSENT: Cal Finocchiaro, Manjula Karamcheti V. APPROPRIATIONS

A. (ID # 2026-1784): Requesting the Appropriation of $2,976,462 which includes $115,000 previously appropriated for the Feasibility and Schematic Design Cost on December 1, 2025 for the purpose of paying costs of installing a new roofing system for the Learning Commons at Melrose High School. Elena Proakis-Ellis, DPW Director, and Kathryn Armata, Treasurer, shared that this is the standard MSBA language that's been approved by both our bond council and the MSBA program, in association with the Learning Commons Roof project. This is the next step in that process to implement the roof replacement, which is scheduled to occur this coming summer. The total project cost is $2,976,462, inclusive of the $115,000 that council has already approved, and that is paid out of free cash. So the amount they're asking for approval for is $2,861,462 for the bonding. And they anticipate borrowing probably a little bit over the 49% of that number, and the rest will be reimbursed. They hope to stay in the 48% reimbursement rate regardless of change orders, since there is a lot of contingency already built into the price. The current roof is 29-30 years old, and the new one will probably have a standard 10-year warranty, and they expect to get more years of use from it. Council asked if it makes sense to pay for the $1.4 from free cash instead of taking on the 25-year debt at 4.5% to save money and Kathryn will consult with CFO Golden on this. This portion of the roof is over the Learning Commons, has no skylights or solar panels and construction will take place summer of 2027. Motion to Recommend made by President Freeman Seconded by Councilor Vandiver All were in favor and motion passed RESULTS: ACCEPTED [UNANIMOUS] TO: City Council AYES: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams NAYS: None ABSENT: Cal Finocchiaro, Manjula Karamcheti VI. ORDERS

A. (ID # 2026-1910): Authorization to Execute Lease Agreement: five-year lease agreement with All American Investment Group, LLC for the purchase of a new 2026 Vactor Sewer Truck Elena Proakis-Ellis, DPW Director, stated that this is the same truck that she came before council with in the spring for free cash. Council allocated $150,000 of sewer free cash at that time to be 3 combined with some operating budget as the down payment, and then this was a five-year lease. This was always the plan. Since it is a five-year lease, it qualifies as requiring a vote of the city council, because it's an agreement longer than three years. Council asked if the city should consider purchase of the truck instead of a lease agreement. The truck will be leased in order to stabilize and keep predictable the water and sewer rates. It's better to meter out the payments over a number of years instead of having one large payment in a single year, and the payment is already built into the sewer operating fund. The lifespan of a Vactor truck is 10 years, and the city's current truck is 11 years old and in need of costly repairs. Motion to Recommend made by Councilor Park Seconded by Councilor Vandiver All were in favor and motion passed RESULTS: ACCEPTED [UNANIMOUS] TO: City Council AYES: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams NAYS: None ABSENT: Cal Finocchiaro, Manjula Karamcheti

B. (ID # 2026-1912): Authorization to Acquire two Parcels of land- G7 0 111 and G7 0 112- located in the City of Melrose, at their assessed value, to be used for stormwater management, using funds made available through the City’s FEMA Building Resilient Infrastructure and Communities (BRIC) grant. Elena Proakis-Ellis, DPW Director, shared that this project dates back several years to our prior city engineer, Vonnie Reese. The project centers around the area of Burnett and Laurel Streets and is a drainage stormwater management project to reduce flooding in these neighborhoods. They got a FEMA BRIC grant at the time and the final piece of the BRIC grant that they have right now is for FEMA to cover 80% of the property transfer and the associated legal fees. Shannon Phillips, City Solicitor, has performed all the legal work surrounding this, along with a lawyer for the sellers and a lawyer for the city. The two parcels are landlocked and undevelopable, and have a drainage channel that runs alongside them, which is a city drainage channel. This land will be used mostly to reduce flooding in the area and the assessed value of the parcels is $12,500 and Melrose will pay 20% and FEMA 80%. Motion to Recommend made by President Freeman Seconded by Councilor Kowal All were in favor and motion passed RESULTS: ACCEPTED [UNANIMOUS] TO: City Council AYES: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams 4 NAYS: None ABSENT: Cal Finocchiaro, Manjula Karamcheti VII. ADJOURNMENT Motion to Adjourn by unanimous consent made by Chair Romanul at 7:35 PM All were in favor and meeting was adjourned 5 To: Mayor Grigoraitis & The Melrose City Council From: Erica Drummond Re: SNAP Community Partner Grant Date: 09/25/2026 The SNAP Community Partner Grant is a collaborative program between the Massachusetts Department of Transitional Assistance and the UMASS Chan Medical School. This program enables community organizations to receive federal reimbursement for conducting approved SNAP outreach and application assistance. As the director for the Melrose Council on Aging and main contact for the Melrose Emergency Fund, I have seen first-hand how difficult it can be for residents to navigate the application process, recertification periods, and general maintenance of their SNAP accounts. Many Melrose residents rely on monthly SNAP funding to purchase food and groceries for themselves and their families. This vital resource can be the difference for Melrose families being able to afford their monthly bills including rent, utility costs, and other critical expenses. As a SNAP Community Partner, our social services team consisting of myself, Social Services Coordinator Rachael Cordella, and our annual Social Services Intern will continue to assist with SNAP applications and recertifications, community outreach, and education for the community. The Council on Aging department will receive federal reimbursement for work we already perform while also gaining access to the DTA Connect Provider Portal. Accessing this portal will make assisting with applications much easier as we will have the direct capability to submit applications, upload supporting documents, and check on the status of residents’ cases. We will also have access to a dedicated DTA community liaison which will seriously reduce the amount of time spent on hold with the DTA customer service hotline. DEPARTMENT OF PUBLIC WORKS Administration–Engineering–Water–Sewer–Facilities Parks–Forestry–Highway–Sanitation–Cemetery–Fleet CITY OF MELROSE City Yard, 72 Tremont Street Elena Proakis Ellis, P.E., BCEE Director of Public Works Melrose, Massachusetts 02176 Telephone – (781) 665-0142 E-mail: eproakis@cityofmelrose.org MEMORANDUM To: Mayor Jennifer Grigoraitis Melrose City Council From: Elena Proakis Ellis, P.E., Director of Public Works cc: Cari Berman, Superintendent of Schools Kerriann Golden, CFO/Auditor Kathryn Armata, City Treasurer/Collector Ken Kelley, Melrose Public Schools Lauren Grymek, Chief of Staff Date: September 28, 2026 Re: MSBA Funding Authorization – MHS Learning Commons Roof The City of Melrose is working with the Massachusetts School Building Authority (MSBA) and our assigned design consultant (RDA) and Owner’s project manager (CSL) on a project to replace the roof over the Melrose High School Learning Commons. The Learning Commons was constructed in 2016 and serves as Melrose High School’s library and technology center, along with a community meeting space. The state-of-the-art fixtures and equipment installed during the $5.3M Learning Commons project are at risk with a leaking roof above, and this roof replacement project is a high priority for both school administration and the DPW Facilities Division to protect this significant investment. Having recently completed the schematic design report, we are now seeking authorization from both the School Committee and the City Council to proceed with funding the final design, construction, and construction administration for this important project. The schematic design report can be viewed here: https://acrobat.adobe.com/id/urn:aaid:sc:VA6C2:8865a37e-2945-4a77-8268-1d32a69de6ce The attached order contains language approved by the MSBA and the City’s Bond Counsel to seek this funding authorization. The total cost estimate for this project is $2,976,462, which includes $115,000 previously appropriated by the City Council through a FY25 Free Cash order for the feasibility study/schematic design components of the project. The requested bond authorization is for the full project cost minus the $115,000 previously appropriated, for a total of $2,861,462. Any MSBA contribution will ultimately reduce to total amount borrowed. The MSBA contribution has been assigned at 49.94% of the eligible project costs. Please reach out to Kathryn Armata or me if you have any questions about this work or this funding authorization request. Final Version as approved by MSBA – 9/23/2026 CITY OF MELROSE Office of Treasurer-Collector City Hall, 562 Main Street Kathryn J Armata Melrose, Massachusetts 02176 Treasurer-Collector Treasurer - (781) 979-4162 Collector - (781) 979-4120 Fax - (781) 665-6877 MEMORANDUM To: Mayor Jen Grigoraitis City Council From: Kathryn Armata Date: September 28, 2025 Re: Requesting the Appropriation of $2,976,462 which includes $115,000 previously appropriated for the Feasibility and Schematic Design Cost on December 1, 2025 for the purpose of paying costs of installing a new roofing system for the Learning Commons at Melrose High School ORDERED: That the City appropriate the amount of Two Million Nine Hundred Seventy-Six Thousand Four Hundred Sixty-Two Dollars ($2,976,462), which includes $115,000 previously appropriated for the Feasibility and Schematic Design Cost on December 1, 2025, for the purpose of paying costs of installing a new roofing system for the Learning Commons at Melrose High School, located at 360 Lynn Fells Parkway, Melrose, MA, including installation of ladder access, louver replacement, an alternative EPDM roofing system, new drain bowls and replacement of the through-wall flashing, and including the payment of all costs incidental or related thereto (the “Project”), which proposed repair project would materially extend the useful life of the school and preserve an asset that otherwise is capable of supporting the required educational program, and for which the City may be eligible for a grant from the Massachusetts School Building Authority (“MSBA”), said amount to be expended under the direction of the Melrose School Committee. To meet this appropriation, the Mayor is authorized to borrow said amount under M.G.L. Chapter 44, or pursuant to any other enabling authority. The City acknowledges that the MSBA’s grant program is a non-entitlement, discretionary program based on need, as determined by the MSBA, and any project costs the City incurs in excess of any grant approved by and received from the MSBA shall be the sole responsibility of the City provided further that any grant that the City may receive from the MSBA for the Project shall not exceed the lesser of (1) forty nine and ninety-four hundredths percent (49.94%) of eligible, approved project costs, as determined by the MSBA, or (2) the total maximum grant amount determined by the MSBA; and that the amount of borrowing authorized pursuant to this vote shall be reduced by any grant amount set forth in the Project Funding Agreement that may be executed between the City and the MSBA 71950985 v2 WATER AND SEWER RATE ADVISORY COMMITTEE CITY OF MELROSE Ken Truesdale, Resident Representative, Chair Melrose City Yard, 72 Tremont Street Kathryn Armata, Treasurer/Collector Melrose, Massachusetts 02176 Kerri Golden, CFO/Auditor Elizabeth Kowal, City Council Representative Telephone - (781) 665-0142 Jim O’Loughlin, Resident Representative Elena Proakis Ellis, P.E., Director of Public Works Jay Coy, Acting City Engineer MEMORANDUM To: Melrose City Council From: Water and Sewer Rate Advisory Committee cc. Mayor Jen Grigoraitis James Troup, DPW Lisa Patterson, DPW Jennifer Rosa, DPW, Water and Sewer Committee Clerk Date: April 8, 2026 Re: Summary of FY27 Water and Sewer Rate Orders The Water and Sewer Rate Advisory Committee, consisting of the members listed above, respectfully submits the following water and sewer rate recommendations for FY27. They are recommended by unanimous vote of the committee. The FY27 revenue requirements for the water and sewer enterprise funds can be met using the FY26 water and sewer rates, with no increases to either volumetric rates or base fees. The FY27 rates benefit from modest increases in the MWRA water and sewer assessments and lower debt repayment obligations in FY27 in the sewer fund compared to FY26. The sewer assessment has only increased moderately due to continued reductions in sewer flows resulting from the City’s ongoing efforts to remove extraneous flows (groundwater infiltration and rainwater inflow) from the sanitary sewer system. As you may recall from prior years, we target reserve fund balances of 10% of annual operating expenses for each fund. Based on the budgeted revenue requirements for FY27, the reserve funds are presently at just over 10% of each fund’s operating budget, thus no transfers are recommended into the water and sewer reserve funds for FY27. Water and Sewer Rate Advisory Committee Recommendations Page 2 April 8, 2026 Thus far in FY26, water use has met or exceeded our projections in last year’s rate model. As a result, the water and sewer enterprise funds are projected to have sufficient revenue to cover expenses as we come to the close of FY26. Therefore, we are not recommending any retained earnings be used this year to cover revenue shortfalls. With no proposed changes to the water and sewer rates for FY27, the recommended rates are shown below, matching FY25 and FY26 rates. Proposed FY27 Water and Sewer Rates Proposed FY26 Volumetric Rates Water (per 100 cf) Sewer (per 100 cf) Tier 1 $8.32 $12.25 Tier 2 $11.15 $15.43 Proposed FY26 Base Fees (meter size) Water (per meter) Sewer (per meter) 5/8” $20.33 $26.38 3/4” $20.33 $26.38 1” $20.33 $26.38 1.5” $79.53 $103.58 2” $123.93 $161.48 3” $227.53 $296.58 4” $375.53 $489.58 6” $745.53 $972.08 $20.33 2nd Meter Fee -- ($50.00 if not upgraded) In addition to these rates, the Committee respectfully recommends the following: 1. No transfers to reserves from either water or sewer free cash for FY27, as noted above. 2. A free cash allocation from the Sewer Enterprise Fund in the amount of $150,000 for a downpayment on the replacement of the City’s Vactor truck. No free cash is requested from the Water Enterprise Fund at this time. 3. No recommended changes to ordinance language in Section 228, Water, Sewer, and Drains pertaining to rates. The Water and Sewer Rate Advisory Committee submitted a memo in April 2025 related to water and sewer discount programs. Our committee is continuing our work evaluating options for the future of these programs. Although we are not making any recommendations at this time regarding acting on the items covered in the memo, it is attached hereto, for the information of the City Council, especially for the benefit of new members of the Council. We appreciate your consideration of these items and are happy to answer any questions you may have. We look forward to continuing the important work of our committee in FY27 to provide fiscally responsible and sustainable water and sewer rates for the Melrose community. LEASE WITH OPTION TO PURCHASE AGREEMENT Agreement No. «Agreement_Number» Lessee Lessor «Lessee_Name» All American Investment Group, LLC «Lessee_Address» N7818 State Park Rd. «Lessee_City», «Lessee_State» «Lessee_Zip» Sherwood, Wisconsin 54169 Dated as of «Schedule_Date» This Lease With Option to Purchase Agreement dated as of the date listed above is between Lessor and Lessee listed directly above. Lessor desires to lease the Equipment described in Exhibit "A" to Lessee and Lessee desires to lease the Equipment from Lessor subject to the terms and conditions of this Agreement which are set forth below. I. Definitions: Section 1.01. Definitions. The following terms will have the meanings indicated below unless the context clearly requires otherwise: "Agreement" means this Lease with Option to Purchase Agreement and all Exhibits and Appendices attached hereto. "Budget Year" means the Lessee's fiscal year. "Commencement Date" is the date when Lessee's obligation to pay rent begins. "Equipment" means all of the items of Equipment listed on Exhibit "A" and all replacements, restorations, modifications and improvements. “Legally Available Funds” means funds that the governing body of Lessee duly appropriates or are otherwise legally available for the purpose of making Rental Payments under this Agreement, including monies held in the Vendor Payable Account to the extent that such moneys are used to prepay Rental Payments or Purchase Option Price. "Lessee" means the entity listed above as Lessee and which is leasing the Equipment from Lessor under the provisions of this Agreement. "Lessor" means the entity originallySAMPLE listed above as Lessor or any of its assignees. "Lease Term" means the Original Term and all Renewal Terms. "Original Term" means the period from the Commencement Date until the end of the Budget Year of Lessee. “Partial Prepayment Date” means the first Rental Payment date that occurs on or after the earlier of (a) the twenty-four month (24) anniversary of the Commencement Date or (b) the date on which Lessee has accepted all the Equipment and all of the Equipment has been paid for from the Vendor Payable Account. “Purchase Price” means the total cost of the Equipment, including all delivery charges, installation charges, legal fees, financing costs, recording and filing fees and other costs necessary to vest full, clear legal title to the Equipment in Lessee, subject to the security interest granted to and retained by Lessor as set forth in this Agreement, and otherwise incurred in connection with the financing of this Equipment. "Renewal Term" means the annual term which begins at the end of the Original Term and which is simultaneous with Lessee's Budget Year. "Rental Payments" means the payments Lessee is required to make under this Agreement as set forth on Exhibit "B". "State" means the state in which Lessee is located. “Surplus Amount” means any amount on deposit in the Vendor Payable Account on the Partial Prepayment Date. “Vendor Payable Account” means the separate account of that name established pursuant to Section X of this Agreement. II. Lessee Warranties Section 2.01. Lessee represents, warrants and covenants as follows for the benefit of Lessor or its assignees: (a) Lessee is an "issuer of tax exempt obligations" because Lessee is the State or a political subdivision of the State within the meaning of Section 103(a) of the Internal Revenue Code of 1986, as amended, (the "Code") or because Lessee is a constituted authority or district authorized to issue obligations on behalf of the State or political subdivision of the State within the meaning of Treasury Regulation 1.103-1(b). (b) Lessee is authorized under the Constitution and laws of the State to enter into this Agreement,and has used such authority to properly execute and deliver this Agreement. Lessee has followed all proper procedures of its governing body in executing this Agreement. The Officer of Lessee executing this Agreement has the authority to execute and All American Investment Group, LLC DATE: October 7, 2026 TO: Elena Proakis Ellis – Director of Public Works All American Investment Group, LLC is pleased to provide you with the following tax-exempt lease purchase financing proposal for Melrose, MA - DPW. EQUIPMENT/PROJECT: One (1) New Vactor 2110IDF Sewer Cleaner Truck ACQUISITION COST: $627,500.00 TRADE-IN ALLOWANCE: $ 35,000.00 DOWN PAYMENT: $214,520.06 AMOUNT FINANCED: $377,979.94 LEASE TERM: 5 Years FREQUENCY OF PAYMENTS: Annual in Arrears INTEREST RATE: * 5.70% PAYMENT AMOUNT: $89,000.00 FIRST PAYMENT DUE: 1 year from the financing start date * This rate expires on October 30, 2026. TERMS AND CONDITIONS: • This proposal is subject to credit review, approval and execution of mutually acceptable lease documentation. • Payments under the lease are subject to annual appropriations and to all authorizations required under law. • Lessee shall have an option to purchase the equipment during the lease term, and at the end of the lease term, when all Payments due have been made by Lessee, Lessee shall own the equipment outright. • This transaction will be designated as tax-exempt under Section 265(b)(3) of the IRS Code of 1986. • For credit review, audited financial statements and a budget summary for the current fiscal year will be required. • A documentation fee of $200.00 will be charged for all transactions with an amount financed of less than $100,000.00. The undersigned certifies under penalties of perjury that this bid or proposal has been made and submitted in good faith and without collusion or fraud with any other person. As used in this certification, the word “person” shall mean any natural person, business, partnership, corporation, union, entity, or group of individuals. Please don’t hesitate to call or email me if you have any questions or need more information. Ron Klein, President All American Investment Group, LLC N7818 State Park Road, Sherwood, WI 54169 Phone: 303-623-5100 Cell: 970-596-5353 CONFIDENTIALITY NOTICE: This facsimile or email or email transmission and any accompanying documents contain information belonging to the sender which may be confidential and legally privileged. This information is intended only for the use of the individual or entity to whom this facsimile or email was sent as indicate above. If you are not the intended recipient, any disclosure, copying, distribution, or action taken in reliance on the contents of the information contained in this facsimile or email is strictly prohibited. Thank you. DEPARTMENT OF PUBLIC WORKS Administration–Engineering–Water–Sewer–Facilities Parks–Forestry–Highway–Sanitation–Cemetery–Fleet CITY OF MELROSE City Yard, 72 Tremont Street Elena Proakis Ellis, P.E., BCEE Melrose, Massachusetts 02176 Director of Public Works Telephone – (781) 665-0142 E-mail: eproakis@cityofmelrose.org MEMORANDUM To: Melrose City Council cc: Jennifer Grigoraitis, Mayor Shannon Phillips, City Solicitor Jay Coy, City Engineer Date: September 29, 2026 Re: Laurel Street Parcels Property Acquisition The Department of Public Works respectfully requests City Council approval to purchase two vacant, landlocked parcels proposed for acquisition through the City’s FEMA Building Resilient Infrastructure and Communities (BRIC) grant-funded project. These parcels are located behind residential properties on Laurel Street to the north, Sycamore Road to the east, and Burnett Street to the south, and together total approximately 49,359 square feet. The parcels consist of isolated wetlands with a drainage channel running along the southern borders, making the area entirely undevelopable. By obtaining ownership of this land, the City will strengthen its ability to manage stormwater, preserve sensitive environmental resources, and implement both current and future flood protection measures. Prior to submitting the BRIC grant application, the property owners agreed to sell both parcels to the City at their assessed values, with the intention that they be used exclusively for stormwater or environmental purposes, which aligns with the City’s needs and long-term resiliency goals. The assessed-value purchase prices for the parcels are $7,200 and $5,300. The purchase of these properties, as well as the associated legal fees related to necessary title research and court filings, will be funded through available funding of the BRIC grant. The City Solicitor has reviewed this transaction, and the related deeds and has approved them as to legal form. We respectfully request approval to proceed with the purchase of these parcels in accordance with the attached deeds. Please let us know if any additional information is needed.

Transcript

▶ 0:00 All right. Good evening. The time is 7:00 PM on Monday, October 19th, 2026. This is a meeting of the Appropriations and Oversight Committee. My name is Devin Romanul. I am the chair. Joining me this evening are Vice Chair Vandiver, Councilors Chen, Jamaleddine, Kowal, Obremski, Park, Williams, and President Freeman. This serves as a notice of quorum for the record. And in accordance with open meeting law, this is being broadcast and recorded live on MMTV. At this time, I'll motion by unanimous consent to approve that reading the minutes from our most recent meeting on September 28th. Seeing no objection, those minutes are now approved. I'll now motion by unanimous consent to open the floor for public comment.

▶ 0:43 Seeing no objection, we are now open for public comment. This is a portion of the meeting where members of the public may speak on any item on tonight's agenda. Comments expressing other views, other matters are also welcome. Do we have anybody here for public comment? Seeing none, do we have anybody online? No one online. All right. Seeing no people for public comment. Going once, going twice. If there's no objection, I'll motion by unanimous consent to close public comment. Seeing none, we are now closed for public comment. Up first on tonight's agenda under grants, item number 2026-1860, acceptance of a grant in the amount of $2,385.92 for staff time assisting or promoting SNAP applications.

▶ 1:32 Good evening. How are you? Good evening, Councilors. Thank you as always for having me. So the grant before you tonight is a partnership between the Department of Transitional Assistance and UMass Chan Medical School, and they develop community partners in residential communities who can assist with applying, recertifying, and checking on the status of SNAP and DTA accounts. So, we see a lot of residents who take advantage of these programs to help with purchasing groceries and other monthly necessities. So, this is something that our office at the Council on Aging assists with on a normal basis anyway. So, this would be a great opportunity to be reimbursed for some of our work. Some of the other benefits of this program would be that we would gain

▶ 2:29 access to the DTA provider portal, which would give us much easier access to assist with applications directly. We could check on the status of pending applications and assist with recertifications. And then you also get access to a liaison with the DTA office. So just making things much more accessible and easier for us to assist and make things quicker. So usually right now we have to call the 800 number just like anybody else, and wait on hold with folks. So that's primarily what I'm excited about with this grant. So, I'm happy to take any questions. Great. Thank you so much. Up first, I have Vice Chair Vandiver. This sounds wonderful. I motion to recommend. Second. Motion to recommend made by Vice Chair Vandiver, seconded by Councilor

▶ 3:20 Williams on discussion. Do my colleagues have any questions? Councilor Chen. Have you seen an increase in SNAP benefit requests in the past couple of years? Yeah, just as things get more expensive these days, cost of living, we've seen a definite increase in traffic to our office for things like this and other emergency needs. So, we're hoping this will have a big impact on the community as we can assist further. Do we have an estimate of how many people are on SNAP benefits from your demographic that you work with? I would say more than 50% in my demographic, just because most of them are on a fixed income. But I don't have exact numbers for you on that. And once people enroll, are they in the program and they don't need much more

▶ 4:12 assistance, or do they need help to- So they do have to recertify every year, which can be difficult for some folks. I think they do have a paper version, but they're moving towards online. So that can be a difficult process for folks. They have to provide supporting documents and things like that. So that's part of why access to the portal would be really great because we can upload those documents directly, and make sure people don't lose access to their benefits for silly research mistakes or things like that. Great. Thank you so much. Perfect. Up next I have Councilor Jamaleddine. Thank you. Thank you. This is really exciting. How many staff worked on this? From the way that I'm reading the order, it says, "For staff time spent assisting

▶ 5:01 with or promoting SNAP applications." Do you have any idea how many hours were put with SNAP or how many staff? Sure. So, the Council on Aging office, we have a social services team, if you will, but it's primarily me. Rachel Cordella is the social services coordinator. And then we do get an annual social services intern who is a big help as well. So it's the three of us primarily who are working on cases. Rachel's part-time, 18 hours a week, as well as the intern part-time. So, between the three of us, somebody's always available in the office. Through this grant, we can only really ask for reimbursement for time directly spent on SNAP cases. So, that's reflected in the budgets. And it's only a 50% reimbursement.

▶ 5:58 So whatever we submit, it'll be a 50% reimbursement based on basically Rachel's- It's not fixed number. It really depends on how many hours you guys spent or cases you received. Yeah. So it'll be based on cases, and then you can also count community outreach and education. So, we have our resource fair next week. We'll be there. That would count towards something that we could ask for reimbursement for. And is that going to be yearly for next year as well? So if we have- I believe so, yes ... more cases, that would be something that we can also apply for it? Mm-hmm. Yes. As a grant. That's awesome. And you mentioned about a new program that with the electronic, all the documents, all the records would be there. Who's going to be handling that?

▶ 6:47 Is it the same social worker- Yes ... Rachel and you and the other part-time? Yes. So the three of us would have access to that system. And it would all be housed within that online portal, so. Okay. And you will have the capacity because this is definitely another load or task that you're going to be responsible of. Is that something within your capacity? Yes, I definitely think it's within our capacity, and it's things that we end up doing anyways, but it takes longer than what it will take here. So- Okay ... hopefully it'll balance out as we get maybe more demand, it'll be easier to meet that demand. Okay. And is it for a certain age? Because I know Rachel is only handling over 62, right?

▶ 7:38 So, Rachel kind of has a dual role where, primarily we serve folks who are 60 and older. But at the Council on Aging office, we also oversee the Melrose Emergency Fund. So if a case comes in in the emergency fund, we do take any age. So we do see a good mix of clientele that we work with. And, it could be anywhere from children to older. Okay. So for those that are listening or anyone is asking for SNAP, they can reach out to you regardless of their age. Yeah. That's accurate. Mm-hmm. Okay. Thank you so much. Yep. Other councilors on discussion? We have a motion on the floor. They seconded. Seeing no other comments, Madam Clerk, will you please call the roll? Councilor Vandiver? Yes. Councilor Chen?

▶ 8:33 Yes. Councilor Jamaleddine? Yes. Councilor Kowal? Yes. Councilor Obremski? Yes. Councilor Park? Yes. Councilor Williams? Yes. President Freeman? Yes. Chair Romanul? Yes. All in favor. All in favor, that motion will pass and be referred to the full city council at our next meeting. Thank you, guys. Thank you so much. Have a great night. Up next, ID number 2026-1784, requesting the appropriation of $2,976,462, which includes $115,000 previously appropriated for the feasibility and schematic design cost on December 1st, 2025, for the purposes of paying costs and of installing a new roofing system for the Learning Commons at Melrose High School. Good evening. Good evening Thank you for having us. The motions before you is the standard MSBA language that's been

▶ 9:28 approved by both our bond council and the MSBA program, in association with the Learning Commons Roof project that I had presented to you in the spring for-- Actually, it was even before that when we did the statement of interest. And so this is just the next step in that process to implement the roof replacement, which is scheduled to occur this coming summer. And just to clarify, because I know the numbers are all over the place, the total project cost is the 297,646,262, inclusive of the 115 that you have already approved, and that is paid out of free cash. So the amount we're asking for approval on is 2,861,462 for the bonding. And we anticipate borrowing probably a little bit over the 49% of that number, and

▶ 10:23 the rest will be reimbursed. Great. Thank you very much. Any questions from my colleagues? President Freeman. Just a question on the reimbursement from MSBA. I understand that once the project has started, that comes in at a certain point. So you said we'll only bond for the non-borrowed portion, assuming that that other portion comes in prior to the first payment being due. Is that kind of how that works or? Either that or the city would float little periods in between- Okay ... but we have to show the worst-case scenario, which is we don't get any reimbursement at all. Okay. And the MSBA has indicated thus far that our reimbursement percentage for the overall project is 49.94%, but we just had a recent call with them with the

▶ 11:09 updated budget from our 60% design, and we are down to them covering about 48.25%. So we didn't lose much in what they determined to be eligible costs once they analyzed the budget spreadsheet. So that's good news. Sometimes with change orders and such, if you have a change order for something that's not traditionally MSBA eligible, then the city may have to float the cost of that. But there's a lot of contingency already built into the prices. So, even if we had to cover the whole thing, these numbers would cover the whole thing with contingencies. But our hope is to stay in that 48% reimbursement rate. Wonderful. Thank you very much. Up next, Councillor Park. Thank you. Quick question about the roof replacement itself and the logistics in terms of

▶ 12:01 once this roof is completed, do we have an expected warranty in terms of how long that roof will last? I ask because the Learning Commons was built in 2016. It's looking to be replaced in 10 years from now. The roof wasn't replaced in 2015, so when they did that project, they determined that the roof was in good enough condition to just put coating on it. But the roof, in order to qualify for MSBA, I believe your roof has to be at least 30 years old, over 29 years old. Okay. And this roof qualifies. So the roof is very old and is definitely beyond its useful life. Okay. Thank you. And can you just give me a rough timeline in terms of how long this will last? Yeah. I think most of the roof warranties that we get are 10 years, but the hope is that

▶ 12:51 these roofs have a 25 to 30-year lifespan, similar to the ones that are on now. Very good. Thank you. Up next, Councillor Chen. All right. Thank you. So to clarify, it costs about $2.8 million. We plan to get almost half of that, like $1.4 million from the MSBA, then we're going to borrow effectively $1.4 million. I saw it was a 25-year debt at 4.5%, so that's what we'll have to pay every year for the interest payment, I guess, would be around a million dollars for the principal and interest, the annual payments for the next 25 years. But that would be on the $1.4 million that we're borrowing, not the full 2.8. Right. Yes, we'd have to legally show the schedule for the 2.8. Yeah. Essentially, it's half of that.

▶ 13:45 This is an estimate based on that particular date that was done. The market moves all the time. We generally price things very conservatively- Yeah ... just so that we don't want to get surprised with a higher number in the future. But yes, you have the correct assumption. So I'm just thinking with bond rates being high and going higher, maybe since this is happening, does it make sense to try to pay for this more in free cash in the next few years and- That would be a question to CFO Golden. To- That would be a question for CFO Golden. Okay. We would have to discuss that. Because the interest payment on $1.4 million would be about a million dollars at the 4.5% rate. Like, the total interest over the life of the loan.

▶ 14:31 I looked at the- Yeah. Yes ... I think for $2.8 million is about $1.9 million. Yeah. So I'm trying to... It's a scale of money that we can kind of afford in one big lump sum. I'm just not sure if we do this now, would we wish that we had just paid for it outright and not had to saddle ourselves with interest payments for the next 25 years at a high bond rate? Like, I probably, not the same- Again, I would have to talk to CFO Golden about that and what the options are. I don't know where they have allocated other monies. I'm sorry. Okay. Do we know if can we issue or borrow now, and then if we decide to pay off, if it's better for us just to pay it off sooner, can we do that? We would have to take a look at any kind of restrictions within that

▶ 15:27 debt agreement generally around. Okay. And where are we at? Go ahead. We don't usually borrow, though, until we're like- Ready ... Yeah, about to do the project. So we would be borrowing the design funds pretty much right away because that's the first part that we need to pay for right away. Mm-hmm. But if we were, when free cash comes around next spring, we wouldn't be under construction yet, so we wouldn't have borrowed construction funds yet. So if Harry Golden felt that it was wise to shift some of it to free cash, that would be something that would still be feasible. We wouldn't have borrowed all the money yet in the spring. Okay. Yeah. Got it. And where does this put us on our total debt borrowing

▶ 16:10 amount? We have sufficient capacity. I can send you a schedule. I can't remember what it was from. Where things have been rolling off lately, so this would be a replacement. And then we have public safety coming on as well, and- Yes, that's- But that's actually through. All right. Okay. Thank you. Thank you. Up next, Councillor Williams. Thank you. I was going to ask a similar line of inquiry to Councillor Chen, and I'll try not to duplicate any of that, but on the website, we say that in December 2025, we got a rate of like 3.8 on $30 million in bonds. I can't remember if we've had any major bond sales since then in- We had the public safety building bond sale in December, I believe. Of '25.

▶ 16:59 Yes. Yeah. That was the one I'm talking about. It was 30 million for 3.8 or something. But we haven't gone out to bid for anything else bond-wise. So we don't really... Yeah. So I don't know what the market rates are for 30-year bonds. I know that the bond market is yo-yoing like crazy at the moment. But yeah, I think it's a fair question to ask. Sure. Like, if you're thinking about something that's under, like, a couple of million dollars where a big free cash lump could absorb it, is it worth it to cut into the interest, especially if you consider the benefit of saving money? Or is it worth it to do a 30-year note and have a cash flow benefit? Historically, we've been sort of restricted on cash flow more than we have on debt

▶ 17:43 capacity. So I feel like it's probably comfortable for us to do this, but that's a good thing, I guess, to think about. Substantive question, where on the roof does this come close to the skylight that we had an issue with? Am I misremembering this? Not the same. Okay. It's near the skylights, but it's not the same roof that the skylights are part of. Okay. Yeah. All right. So this will probably not touch the outer... Is it one continuous flat surface? Yes. Or is it just a portion of the roof? Is it just the roof over the commons? It's the roof over the learning commons. Yeah. It's kind of a square with a triangle that comes off of it. If you look at an aerial, you'll probably see what I'm talking about.

▶ 18:26 It's a Square with one side that has a triangle that comes off. So we're not cutting into... It's an entire replacement. We're not patching into any part. Right. Yeah. Okay, good. Yeah. That's what I was asking. Are there any panels on it, on this portion? Solar panels? Yeah. No. Okay. Well MSBA does prefer that we build things solar ready- Yeah ... but once you account for the HVC equipment and the piping and the other things that are up there- Probably all the way, yeah ... there's basically no room left. Yeah. And we've been told that we can get a waiver from the requirement because we have so much solar already on the high school roof- And a lot of it ... that we qualify to not have to put in.

▶ 19:03 If it was 20 square feet of available solar, they're not going to make us do that. Yeah. And you were saying, just to refresh my memory, you were saying that you don't think that you're even going to be started on construction with this until summer next year. The entire construction will take place during the summer next year. Next year. Yeah, obviously. Okay. Yeah. Summer 2027. Okay. Thank you. Any other colleagues have questions? President Freeman. Just make a motion to recommend. Second. Motion to recommend made by President Freeman, seconded by Vice Chair Vanderberg. On discussion. Seeing none, Madam Clerk, will you please call the roll? Yes. Vice Chair Vanderberg? Yes. Councilor Chen?

▶ 19:45 Yes. Councilor Jamaleddine? Yes. Councilor Kowal? Yes. Councilor Obremski? Yes. Councilor Park? Yes. Councilor Williams? Yes. President Freeman? Yes. Chair Romanul? Yes. All in favor. All in favor, that will be reported affirmatively to the next full city council meeting. Thank you. Thank you very much. Up next, order number ID 2026-1910, authorization to execute lease agreement, five-year lease agreement with All American Investment Group LLC for the purchase of a new 2026 Vactor sewer truck. Yes, thank you. So this is the same truck that I came before you with in the spring for free cash. We allocated $150,000 of sewer free cash at that time to be combined with a little bit of operating budget as the down payment, and then this was a

▶ 20:35 five-year lease. This was always the plan. We just recently flagged it because of the five-year lease, it qualifies as requiring a vote of the city council because it's an agreement longer than three years. Great. Thank you very much. Do I have any questions from my colleagues? Councilor Chen. Thanks. The cost of this was around $340,000? $627,000. Okay. With a small trade-in value for the existing truck of about $35,000. Does it make sense to just buy it outright instead of lease, or what was the decision-making in- So interestingly, the finance department typically prefers to buy things outright, and that's why we've done that with all of our other vehicles. But with the water and sewer funded,

▶ 21:20 a purchase this large through the water and sewer funds, our goal is to keep rates fairly stable and predictable. And so we've had a capital allocation in the sewer fund for several years now, for about 10, 11 years now, that is meant to cover the payment for the specific truck. So it just stabilizes the rate. We'd prefer not to have a large hit in one year and then coming back down off of that in future years with rates. It's just better to meter it out over the years. And the payment is already built into the sewer operating fund. Thank you. All right, other questions? Councilor Williams. $150,000 covers five years of this? 90,000 covers the five-year payments. 90,000. 150 was part of the down payment.

▶ 22:19 Yeah. And the other part of the down payment, which is about 87,000, is going to come from operating budget. Okay. So you're going to put in the operating budget, the lease payment? The lease payment's already in the operating budget. Oh, okay. All right, cool. Okay, thanks. Okay. Excellent. Other questions? Motion to recommend. Motion to recommend made by Councilor Park. Second. Seconded by Vice Chair Vanderberg. On discussion. Councilor Chen. Tell us about our current Vactor truck and why we need to replace it. Sure. So the lifespan on a Vactor truck is about 10 years. We use it to both jet clean and suck up wastewater, stormwater, cleaning catch basins. Well, some of cleaning catch basins.

▶ 23:08 Vacuum excavation, which is basically sucking up dirt and rocks and such, and so these pieces of equipment take a real beating, and the lifespan's about 10 years. This one is about 11 years old and was similarly purchased with a five-year lease 11 years ago. In recent years, we've been spending over 30,000 a year to fix it. And it had leaks right now in the water, fortunately in the clean water tanks. But it's reaching the point where it's just not worth continuing to pour money into it. Thank you. Mm-hmm. Any other questions on discussion? Seeing none, Madam Clerk, will you please call the roll? Yes. Vice Chair Vanderberg? Yes. Councilor Chen? Yes. Councilor Jamaleddine? Yes. Councilor Kowal? Yes. Councilor Obremski?

▶ 23:56 Yes. Councilor Park? Yes. Councilor Williams? Yes. President Freeman? Yes. Chair Romanul? Yes. All in favor. All in favor, that will be reported affirmatively to our next full city council meeting. Thank you very much. And last but not least, ID number 2026-1912. Authorization to acquire two parcels of land, G70111 and G70112, located in the city of Melrose at their assessed value, to be used for stormwater management using funds made available through the city's FEMA Building Resilient Infrastructure and Communities, or BRIC, grant. Thank you. So this project dates back several years to our prior city engineer, Vonnie Reese. The project centers around the area of Burnett and Laurel Streets.

▶ 24:48 It's a drainage, a stormwater management project, to reduce flooding these neighborhoods. We got a FEMA BRIC grant at the time. I believe it's a 2023 BRIC grant. And part of that grant, that was for designing this project and also for the property acquisition. Thus far, we have not been successful in getting grant funding to construct this project. But the final piece of the BRIC grant that we have right now is for FEMA to cover 80% of the property transfer and the associated legal fees. So we don't want to miss this opportunity. The grant cycle is coming to a close. The deadline, I believe, is January. So if we're going to move forward with the property purchase, which we recommend that we do,

▶ 25:36 we have to do that at this time. Shannon Phillips has performed all of the legal work surrounding this, along with a lawyer for the sellers and a lawyer for the city. And so everything has now been pulled together with the deeds and everything, and we're all ready to move forward with this purchase. The two parcels are landlocked. They are undevelopable. They are very wet. And they serve really no other purpose, but they do have a drainage channel that runs alongside them that is a city drainage channel. And we feel it's advantageous to own this property. Great. Thank you very much. Any questions from my colleagues? Councilor Williams. Hello. Hello. It's very interesting to me. So this property's for sale for many, many years, and

▶ 26:31 obviously it's very difficult to build on and it's completely swampland. And you said you couldn't find the money yet to sort of build into it, but what's your long-term vision? We've talked about this. There's like a watershed issue here with the grass in the back of this or north of this, and then it sort of flows down. What's the long-term vision for this? So we have the full design that Stantec did through this grant- Yeah ... involves lining a whole bunch of stormwater pipes up and downstream of this area, creating an enhanced wetland area within the floodplain. Mm-hmm. So allowing more of a relief valve for the stormwater that's presently flooding into some of the homes in the immediate

▶ 27:18 vicinity. Mm-hmm. There would be area excavated out. There would be some dredging of the stream that runs through that area. So the project has a lot of different elements that are aimed at reducing flooding in the neighborhoods and taking advantage of-- We own one parcel already, and that's really the parcel where the bulk of the work would be done, is on the parcel we already own, in terms of excavating out and redistributing the water in the neighborhood. It's like 50,000 square feet, these two parcels. The two parcels. Yeah. Yeah. But the work of the project wouldn't actually take place on the two parcels. It just gives us access and future ownership and protection from anybody trying to

▶ 28:06 do anything else with this land that really is needed for floodplain. Do you think that it could be engineered with a water treatment system, water retention system, that would allow it to be built upon? No. Ever? No. Okay. I think that would be highly unwise in this neighborhood. Mm. Yeah, where we already have major water issues. And the problems that we face throughout the city are that the majority of the watershed or the open rivers and streams in all of Melrose, you probably all know Melrose used to be called Pond Field. There are very few streams left. They're all channelized underground, giving them fixed capacity. So, as flooding events become more severe, there's nowhere additional for that water to

▶ 28:52 go because it's in fixed size pipes. So the wave of drainage engineering these days is daylighting of streams- Mm ... and that sort of thing. So going in the other direction of putting things further underground and then making something buildable is kind of the opposite of the direction we want to go. Sure. As someone who lives a block or two away from there, about the flooding, I concur with the unbuildability of it. Sorry about that. Up next, Vice Chair Vandiver. Thank you. Is the parcel that we own the one that is labeled Burnett Park? Yes. Okay. But it's not a park. Is it a park for recreational purposes? No, it's very interesting. It's not controlled by the Park Commission. It was purchased for-- It's actually in the purchase information from

▶ 29:42 forever ago for that parcel, that it was purchased for drainage and highway department purposes. So it was never actual park land, but it is always, for years, has gone by the name Burnett Park. If you go out there, there is nothing even close to resembling a park. It's just a wetland parcel. Okay. And so this would now connect that to these other two parcels in the middle there, the Burnett Park. It leaves a parcel in between. Oh, there's still one more parcel in there? Yes. Oh. That we still wouldn't own. Okay. Would we attempt to own that last parcel at some point to connect them? I think the owner, the present owner of that last parcel prefers to keep it. But also similarly just wanting it undeveloped.

▶ 30:26 Uh-huh. I think that's his impetus for keeping it. But yeah, my understanding is that there would still be that parcel in between. Okay. Thank you. Perfect. Up next, I have Councilor Chen. Thank you. Do we know how much the assessed value is for both of these, and- Yes, it is- ... 80% of it, and then so we'll pay 20%? Yeah. So the assessed value is what's listed in the deed, so 5,300 for one parcel and- 7,200 ... 7,200 for the other parcel. So we will pay 20% and FEMA will pay 80%. But then interestingly, the legal fees are far more than the worth of the parcels. So they would also pay 80% of that. The total allocation for this item in the budget under the grant is $30,000. Okay. So we should expect an appropriation for about $6,000 from the council?

▶ 31:26 No, we have sufficient operating funds and drainage for that. Okay. Thank you. Yeah, we shouldn't have to come back for anything related. Great. Other questions? Councilor Park? Have you done any analysis on sort of the bigger picture overall in terms of cost savings? So if we were to move forward with this parcel of land and develop the stormwater management, how much savings would we accrue over the years in terms of having this developed? And what are we doing now to deal with this specific stormwater management problem on- So interestingly, a lot of the problem exists on private property. And so those who would benefit from the stormwater management, it's not so much a savings on the city's part, it's more of a prevention of damage on the private

▶ 32:16 property owner's part. So I don't think there is a city savings to purchasing these parcels. I don't think long term we're going to realize savings. The way FEMA looks at projects is they have a benefit-cost analysis, and you have to have a ratio of one or above. So basically, the cost of the construction has to be balanced out by a savings of private property damage, city effort to close roads or whatever else needs to be done if it's overwhelming sewers or other city services that have to be adjusted. They need to see that over the long term of this project, that it pays for itself in prevention of damages. And FEMA views it that way because they step in to help cities and towns fund damages after they've happened.

▶ 33:12 So this is sort of their-- The BRIC stands for Building Resilience and Infrastructure. I don't know what the C is. So the idea is that this would be a good FEMA BRIC application if we can show that it has a BCA above one. It's possible that it won't have a BCA above one, in which case we will just pursue other grant funding, and attempt to fund the project with either state MVP money or congressionally directed spending, EPA grants. There's all different stormwater grants that we can try to chase to get money for this. The construction is on the order of two and a half to 3 million, so it's not insignificant. Probably not a project that we're going to pay out of pocket completely. Okay. Thank you.

▶ 34:03 Great. Other questions? Motion to recommend. President Freeman, make a motion to recommend. Second. Seconded by Councilor Kowal. On discussion? Councilor Williams. Just to throw out there, this is the kind of thing that the Community Preservation Act would pay for. Other questions on discussion? Seeing none, Madam Clerk, will you please call the roll? Vice Chair Vandiver? Yes. Councilor Chen? Yes. Councilor Jamaleddine? Yes. Councilor Kowal? Yes. Councilor Abrumski? Yes. Councilor Park? Yes. Councilor Williams? Yes. President Freeman? Yes. Chair Romanul? Yes. All in favor. All in favor? That motion passes and will be referred to our next full city council meeting. That being our last item on our agenda tonight, I'll now motion by

Original documents