← Appropriations & Oversight Committee · 2026-10-19 · Appropriations & Oversight Committee 10/19/26

Requesting the Appropriation of $2,976,462 which includes $115,000 previously appropriated for the Feasibility and Schematic Design Cost on December 1, 2025 for the purpose of paying costs of installing a new roofing system for the Learning Commons at Melrose High School.

Clerk file 2026-1784 — its full path through the council

Passed · Recommend · moved by Bradley Freeman, seconded by Kim Vandiver Yes: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams.

Agenda original PDF

No further agenda text.

Minutes original PDF

A. (ID # 2026-1784): Requesting the Appropriation of $2,976,462 which includes $115,000 previously appropriated for the Feasibility and Schematic Design Cost on December 1, 2025 for the purpose of paying costs of installing a new roofing system for the Learning Commons at Melrose High School. Elena Proakis-Ellis, DPW Director, and Kathryn Armata, Treasurer, shared that this is the standard MSBA language that's been approved by both our bond council and the MSBA program, in association with the Learning Commons Roof project. This is the next step in that process to implement the roof replacement, which is scheduled to occur this coming summer. The total project cost is $2,976,462, inclusive of the $115,000 that council has already approved, and that is paid out of free cash. So the amount they're asking for approval for is $2,861,462 for the bonding. And they anticipate borrowing probably a little bit over the 49% of that number, and the rest will be reimbursed. They hope to stay in the 48% reimbursement rate regardless of change orders, since there is a lot of contingency already built into the price. The current roof is 29-30 years old, and the new one will probably have a standard 10-year warranty, and they expect to get more years of use from it. Council asked if it makes sense to pay for the $1.4 from free cash instead of taking on the 25-year debt at 4.5% to save money and Kathryn will consult with CFO Golden on this. This portion of the roof is over the Learning Commons, has no skylights or solar panels and construction will take place summer of 2027. Motion to Recommend made by President Freeman Seconded by Councilor Vandiver All were in favor and motion passed RESULTS: ACCEPTED [UNANIMOUS] TO: City Council AYES: Jason Chen, Bradley Freeman, Maya Jamaleddine, Elizabeth Kowal, John Obremski, Christopher Park, Devin Romanul, Kim Vandiver, Ryan Williams NAYS: None ABSENT: Cal Finocchiaro, Manjula Karamcheti VI. ORDERS

All documents for this meeting on the city portal

Transcript (~11 min @ 9:05)

▶ 9:28 approved by both our bond council and the MSBA program, in association with the Learning Commons Roof project that I had presented to you in the spring for-- Actually, it was even before that when we did the statement of interest. And so this is just the next step in that process to implement the roof replacement, which is scheduled to occur this coming summer. And just to clarify, because I know the numbers are all over the place, the total project cost is the 297,646,262, inclusive of the 115 that you have already approved, and that is paid out of free cash. So the amount we're asking for approval on is 2,861,462 for the bonding. And we anticipate borrowing probably a little bit over the 49% of that number, and

▶ 10:23 the rest will be reimbursed. Great. Thank you very much. Any questions from my colleagues? President Freeman. Just a question on the reimbursement from MSBA. I understand that once the project has started, that comes in at a certain point. So you said we'll only bond for the non-borrowed portion, assuming that that other portion comes in prior to the first payment being due. Is that kind of how that works or? Either that or the city would float little periods in between- Okay ... but we have to show the worst-case scenario, which is we don't get any reimbursement at all. Okay. And the MSBA has indicated thus far that our reimbursement percentage for the overall project is 49.94%, but we just had a recent call with them with the

▶ 11:09 updated budget from our 60% design, and we are down to them covering about 48.25%. So we didn't lose much in what they determined to be eligible costs once they analyzed the budget spreadsheet. So that's good news. Sometimes with change orders and such, if you have a change order for something that's not traditionally MSBA eligible, then the city may have to float the cost of that. But there's a lot of contingency already built into the prices. So, even if we had to cover the whole thing, these numbers would cover the whole thing with contingencies. But our hope is to stay in that 48% reimbursement rate. Wonderful. Thank you very much. Up next, Councillor Park. Thank you. Quick question about the roof replacement itself and the logistics in terms of

▶ 12:01 once this roof is completed, do we have an expected warranty in terms of how long that roof will last? I ask because the Learning Commons was built in 2016. It's looking to be replaced in 10 years from now. The roof wasn't replaced in 2015, so when they did that project, they determined that the roof was in good enough condition to just put coating on it. But the roof, in order to qualify for MSBA, I believe your roof has to be at least 30 years old, over 29 years old. Okay. And this roof qualifies. So the roof is very old and is definitely beyond its useful life. Okay. Thank you. And can you just give me a rough timeline in terms of how long this will last? Yeah. I think most of the roof warranties that we get are 10 years, but the hope is that

▶ 12:51 these roofs have a 25 to 30-year lifespan, similar to the ones that are on now. Very good. Thank you. Up next, Councillor Chen. All right. Thank you. So to clarify, it costs about $2.8 million. We plan to get almost half of that, like $1.4 million from the MSBA, then we're going to borrow effectively $1.4 million. I saw it was a 25-year debt at 4.5%, so that's what we'll have to pay every year for the interest payment, I guess, would be around a million dollars for the principal and interest, the annual payments for the next 25 years. But that would be on the $1.4 million that we're borrowing, not the full 2.8. Right. Yes, we'd have to legally show the schedule for the 2.8. Yeah. Essentially, it's half of that.

▶ 13:45 This is an estimate based on that particular date that was done. The market moves all the time. We generally price things very conservatively- Yeah ... just so that we don't want to get surprised with a higher number in the future. But yes, you have the correct assumption. So I'm just thinking with bond rates being high and going higher, maybe since this is happening, does it make sense to try to pay for this more in free cash in the next few years and- That would be a question to CFO Golden. To- That would be a question for CFO Golden. Okay. We would have to discuss that. Because the interest payment on $1.4 million would be about a million dollars at the 4.5% rate. Like, the total interest over the life of the loan.

▶ 14:31 I looked at the- Yeah. Yes ... I think for $2.8 million is about $1.9 million. Yeah. So I'm trying to... It's a scale of money that we can kind of afford in one big lump sum. I'm just not sure if we do this now, would we wish that we had just paid for it outright and not had to saddle ourselves with interest payments for the next 25 years at a high bond rate? Like, I probably, not the same- Again, I would have to talk to CFO Golden about that and what the options are. I don't know where they have allocated other monies. I'm sorry. Okay. Do we know if can we issue or borrow now, and then if we decide to pay off, if it's better for us just to pay it off sooner, can we do that? We would have to take a look at any kind of restrictions within that

▶ 15:27 debt agreement generally around. Okay. And where are we at? Go ahead. We don't usually borrow, though, until we're like- Ready ... Yeah, about to do the project. So we would be borrowing the design funds pretty much right away because that's the first part that we need to pay for right away. Mm-hmm. But if we were, when free cash comes around next spring, we wouldn't be under construction yet, so we wouldn't have borrowed construction funds yet. So if Harry Golden felt that it was wise to shift some of it to free cash, that would be something that would still be feasible. We wouldn't have borrowed all the money yet in the spring. Okay. Yeah. Got it. And where does this put us on our total debt borrowing

▶ 16:10 amount? We have sufficient capacity. I can send you a schedule. I can't remember what it was from. Where things have been rolling off lately, so this would be a replacement. And then we have public safety coming on as well, and- Yes, that's- But that's actually through. All right. Okay. Thank you. Thank you. Up next, Councillor Williams. Thank you. I was going to ask a similar line of inquiry to Councillor Chen, and I'll try not to duplicate any of that, but on the website, we say that in December 2025, we got a rate of like 3.8 on $30 million in bonds. I can't remember if we've had any major bond sales since then in- We had the public safety building bond sale in December, I believe. Of '25.

▶ 16:59 Yes. Yeah. That was the one I'm talking about. It was 30 million for 3.8 or something. But we haven't gone out to bid for anything else bond-wise. So we don't really... Yeah. So I don't know what the market rates are for 30-year bonds. I know that the bond market is yo-yoing like crazy at the moment. But yeah, I think it's a fair question to ask. Sure. Like, if you're thinking about something that's under, like, a couple of million dollars where a big free cash lump could absorb it, is it worth it to cut into the interest, especially if you consider the benefit of saving money? Or is it worth it to do a 30-year note and have a cash flow benefit? Historically, we've been sort of restricted on cash flow more than we have on debt

▶ 17:43 capacity. So I feel like it's probably comfortable for us to do this, but that's a good thing, I guess, to think about. Substantive question, where on the roof does this come close to the skylight that we had an issue with? Am I misremembering this? Not the same. Okay. It's near the skylights, but it's not the same roof that the skylights are part of. Okay. Yeah. All right. So this will probably not touch the outer... Is it one continuous flat surface? Yes. Or is it just a portion of the roof? Is it just the roof over the commons? It's the roof over the learning commons. Yeah. It's kind of a square with a triangle that comes off of it. If you look at an aerial, you'll probably see what I'm talking about.

▶ 18:26 It's a Square with one side that has a triangle that comes off. So we're not cutting into... It's an entire replacement. We're not patching into any part. Right. Yeah. Okay, good. Yeah. That's what I was asking. Are there any panels on it, on this portion? Solar panels? Yeah. No. Okay. Well MSBA does prefer that we build things solar ready- Yeah ... but once you account for the HVC equipment and the piping and the other things that are up there- Probably all the way, yeah ... there's basically no room left. Yeah. And we've been told that we can get a waiver from the requirement because we have so much solar already on the high school roof- And a lot of it ... that we qualify to not have to put in.

▶ 19:03 If it was 20 square feet of available solar, they're not going to make us do that. Yeah. And you were saying, just to refresh my memory, you were saying that you don't think that you're even going to be started on construction with this until summer next year. The entire construction will take place during the summer next year. Next year. Yeah, obviously. Okay. Yeah. Summer 2027. Okay. Thank you. Any other colleagues have questions? President Freeman. Just make a motion to recommend. Second. Motion to recommend made by President Freeman, seconded by Vice Chair Vanderberg. On discussion. Seeing none, Madam Clerk, will you please call the roll? Yes. Vice Chair Vanderberg? Yes. Councilor Chen?