← Appropriations & Oversight Committee · 2023-04-24 · Appropriations and Oversight Committee Meeting
APPRO-2023-22 : An Appropriation from Sewer Retained Earnings (account # 6000-319000) in the amount of $230,000 and from Water Retained Earnings (account # 6100-319000) in the amount of $440,000. These funds will be appropriated to designated Enterprise Accounts as set forth herein.
Agenda original PDF
Minutes original PDF
APPRO-2023-22 Appropriation An Appropriation from Sewer Retained Earnings (account # 6000- 319000) in the amount of $230,000 and from Water Retained Earnings (account # 6100-319000) in the amount of $440,000. These funds will be appropriated to designated Enterprise Accounts as set forth herein. Ought to Pass Legal & Legislative Committee
Transcript
▶ 32:21 Speaker 1: Councilor McMaster. Yes counselor. Cinello. Yes counselor Eccles. Yes Council. Gerepe. Yes counselor Stewart. Yes Castor crime Shetty. Yes councilor bremski. Yes president Grigoraitis. Yes. And chair. Miglielli. Yes. I've seen him. Yes. Thank you.
▶ 32:40 Leila Migliorelli: Thank you appropriation. 2023-22 Appropriation from sewer routine earnings account number six thousand Dash three one nine zero zero zero in the amount of 230,000 and from water retained earnings account 610-0-319000 in the amount of 440,000. These funds will be appropriated to designated Enterprise accounts is set forth here in tonight. We have Elena prokos Ellis DPW director and Jim true here. Just a point of order in this the way this is written. I just wanted to note that in iqm2. It says that the Appropriations from Seward retained earnings and water retained earnings, but the body of the orders referencing free cash. I just want to make sure that what we have in front of us is correct what I just read out loud, it's a transfer of funds from retained earnings and not from free cash.
▶ 33:37 Speaker 2: That is correct. Okay. Thank you.
▶ 33:43 Speaker 2: so As you know, we always have a robust Capital program in both Water and Sewer each year. And we tend to plan our projects a couple years in advance and especially on the water main side. We do an annual water main program. replacement project and so we had designed several projects a couple years ago. And when we were trying to decide what this year's project should be we knew we're biting off perhaps a little more than we could chew with the with the mwa loan that we apply for every year. So we knew that the prices were likely to come in a little higher we did a base bid and then we did two alternates to see if we could possibly do the complete project this year the streets that we had designed are listed in our memo. They're Trenton Street Noble Road from Henry to Highland. Excuse me, Noah Road and Henry from Highlands to knowell and then we had a small portion of Henry and we had reading Hill Ave. That weren't able to we knew that we That the bids might come in higher than we could afford all of those. So we did those as ADD alternates. So the request on the water main and is that we'd like to be able to construct that complete project Redding Hill Ave is the bulk of the additional cost and as part of our multi-year roadway and utility program. We knew they had a poor roadway conditions a couple years ago. We had the gas company come in and do reading Hill Ave. So now the gas work was done. Completed last year and normally would do the water work the next year and then pave the following year so that the streets only torn up for three years. If we couldn't afford to do it this year, they would be in a state of construction for four years and we don't like to really do that to any neighborhood. So our request is 440,000 from retained earnings toward the water main project. And then on and Sewell Woods is listed there. That was the next street in line that we've also already designed that is also in desperate need of Paving but we don't have the funds. We just couldn't work that one into the program. That's another 500,000 plus So that'll be the First Street on next year's program. And then on the sewer end we had come before you last year requesting $400,000 for generator project at our two largest sewer pump stations. They have Antiquated backup generators that haven't worked in literally decades. We have a portable generator that we run around to five different sewer stations if there's a power outage, which is really not sufficient, especially for the amount of flow these two stations see we have bids in hand now for that project and we're requesting an extra 230,000 from retained earnings for the sewer project.
▶ 36:41 Speaker 3: any questions counselor chromechatie
▶ 36:44 Speaker 2: Hi, thank you so much for being here just real quick. I wanted to make sure that I heard you correctly in terms of what some of the funds will be used for you had mentioned to Henry and Noel and Sewell woods, and so just the funds is for sewer work and for Paving that we couldn't cover in other ways. It's just for the water main work. So the paving work will be done in next year's construction season. So we would patch sometimes these streets end up in better condition just from the construction and the patching then they were before and then we'll pave the following year. But Sewell Woods is not part of the project. That's that will be in next year's construction season. Happened to be driving on Noel today and it really needs some work. So yeah, Noel readinghill and Sewell Woods are all in very bad shape. Yeah. And this would help him move. Further in the right direction of recent put them in line for Paving next year. Okay, great. Thank you. Not sewards but the other two yeah.
▶ 37:50 Mark Garipay: Counselor garepe this is approved on the sewer pump station generator. You said the RFP is ready to go out. When do you think we can get that work to start if we
▶ 37:59 Speaker 2: approve that? So we have we have a contract in hand from the low bidder and actually the low bidders the same company that does our Pump Station maintenance right now. So they would be ready to hit the ground running. However, the timing on the generator delivery is as we saw was City Hall generator. Some some places were waiting upwards of a year to get the equipment but they can do all the prep work. They can get the pad placed get the transfer switches in and then just put the generator in when it comes.
▶ 38:32 Speaker 7: Okay.
▶ 38:37 Speaker 3: Yeah, the counselors cancer crime cheat. No for the first time.
▶ 38:43 Speaker 3: Okay, seeing them counter. I'm Jeannie just like
▶ 38:45 Speaker 2: to make a motion to recommend for Passage.
▶ 38:49 Leila Migliorelli: motion recommend for passage made by councilor Karamcheti seconded by counselor Eccles on discussion
▶ 38:58 Leila Migliorelli: just then I will just might one question point of clarification again since so the request again says the memo says from a free cash request. So this is literally it's coming from retained earnings and going into the Enterprise fund.
▶ 39:13 Speaker 2: So it's coming from the Enterprise funds retained earnings retained earnings. So on the on the water side, we presently have I think it's 453,000 available from prior fiscal years that's already certified. And then on the sewer side we have over 700,000 that's already been certified. So. I sort of use free cash and retained earnings interchangeably, which is why it's it. I've used them interchangeably between me and Jim in the order and in the memo, okay, but these are this is money within the Enterprise fund that is from prior fiscal years and has been certified so Okay, I'm not sure if that would if you would call it free cash in that case. Yeah, probably not. So okay. Thank
▶ 40:01 Speaker 3: you for clarifying that Mr. Core.
▶ 40:06 Speaker 1: Face trademaldine. Yes counselor McMaster. Yes counselor. Sonella. Yes counselor Eccles Yes. Counselgarpe Yes concert Stewart. Yes, Castle crime Shetty. Yes counselor bremski. Yes. President gerritis. Yes and chair mclarely. Yes. That's unanimous ten. Yes, that order